100kW Turbine Installation

July 2009 – Turbine tower delivery

wind-turbine-rhode-island

 

 

 

Click to see tower delivery    

August 2009 - Foundation construction

 

Drill bit for foundation

Drill bit for foundation

Form for pouring concrete

Form for pouring concrete

Rebar "cage" for reinforcement

Rebar "cage" for reinforcement

  September 2009 - Tower is constructed

Second section of the tower goes up

Second section of the tower goes up.

Blades being prepped-view from the tower

Blades being prepped-view from the tower

The nacelle comes in for a landing

The nacelle comes in for a landing.

Installing the blades.

Installing the blades.

September 22, 2009 Turbine is completed!